CONTROL OF VARIATION ORDERS IN THE CONSTRUCTION OF RESIDENTIAL PROJECTS IN MALAYSIA
DOI:
https://doi.org/10.21837/pm.v20i21.1088Keywords:
Control, Residential Projects, Construction, Time and Cost Time ModelAbstract
Variation orders are a frequent occurrence in the construction phase of Malaysian building projects. Increased construction time and costs are inevitable when variation orders appear. The aim of the current research is to identify the effectiveness of a "cost and time model" in controlling variation orders during the construction of residential projects in Malaysia. The model was derived from a literature review, which also examined how case studies and data have been utilised to identify the causes and effects of variation orders. These were analysed using multiple linear regression analysis. Three independent variables were identified as significant positive causes, while two dependent variables were determined to be the effects of a variation order. The independent variables signify the owner’s changes to the scope of work, construction materials and procedures, as well as their modifications to the specifications. The cost and duration of the project is the dependent variables. The model developed was found to be suitable in practice and the authors propose its application in the early stages of residential construction projects to control the occurrence of variation orders in such projects in Malaysia.
Downloads
References
Al-Mayahi, H. T., Ismail, S., Wahab, M. H., Wan Mohd Rani, W. N. M., & Che Amat, R. (2018). Architectural Practices of Project Communication Management in Iraq, Planning Malaysia, 16(5).
Ayman A. Abu Hammad, Souma M. Alhaj Ali, Ghaleb J. Sweis & Adnan Bashir. (2008). Prediction Model for Construction Cost and Duration in Jordan. Jordan Journal of Civil Engineerings. 2(3): 250-266.
Chan, D.W.M. and Kumaraswamy, M.M. (1997) A Comparative Study of Causes of Time Overruns in Hong Kong Construction Projects. International Journal of Project Management, 15, 55-63. DOI: https://doi.org/10.1016/S0263-7863(96)00039-7
Engy Serag, Ph.D.; Amr Oloufa; Linda Malone; and Essam Radwan, (2010). Model for Quantifying the Impact of Change Orders on Project Cost for U.S. Roadwork Construction, Journal of Construction Engineering and Management. Volume 136 Issue 9 - September 2010 DOI: https://doi.org/10.1061/(ASCE)CO.1943-7862.0000206
Hanna, A.S., Taylor, C. S., & Sullivan, K.T. (2005). Impact of Extended Overtime on Construction Labor Productivity. Journal of Construction Engineering and Management. 131(6): 734-739.
Ibbs, C.W, Wong, C.K., & Kwak, Y.H. 2001. Project Change Management System, Journal of Management In Enginering. July 2001: 159-165. DOI: https://doi.org/10.1061/(ASCE)0742-597X(2001)17:3(159)
Ismail, F. D., Kadar Hamsa, A. A., & Ibrahim, M. (2012). Analysis of Factors Influencing the Stated Preference of Academic Employees Towards Telecommuting in IIUM Campus Gombak Planning Malaysia, 10(3).
Mokhtar, A., Bedard, C., & Fazio, P. (2000). Collaborative Planning and Scheduling of Interrelated Design Changes. J. Archit. Eng. ASCE, 6(2): 66-75.
Mohammed Alias Yusof, Noraziah Mohammad & Zulhairuse Mat Derus. (2007). Excusable and Compensable Delays in the Construction of Building Project: A Study in the States of Selangor and Wilayah Persekutuan Kuala Lumpur, Malaysia. Journal of the Institution of Engineers, Malaysia. 68(4): 21–26.
Noraziah Mohammad (2017), Development of Prediction Model for Variation Order in the Construction of Terrace Housing Projects: A Case Studies the State of Selangor, Malaysia. Thesis (PhD/ Doctor of Philosophy), National University of Malaysia Available from https://www.ukm.my/ptsl/portal/ethesis.htm
Sun, S., & Xianhai Meng, X. 2008. Taxonomy for Change Causes and Effects in Construction Projects. International Journal of Project Management. 27: 560-572.
Richard A. Kolawole & Kamau K. Peter & Munala Gerryshom, 2016. Change Order Management Factors in Building Projects in Northern Nigeria, Asian Social Science, Canadian Center of Science and Education, vol. 12(1), pages 223-236,
Tung, Y.-H., Chia, F.-C., & Yong, F. Y.-Y. (2021). Exploring the Usage of Digital Technologies for Construction Project Management, Planning Malaysia, 19(17)
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2022 Noraziah Mohammad, Zabidi Hamzah, Noor Aisyah Mokhtar
This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 3.0 Unported License.
Copyright & Creative Commons Licence
eISSN: 0128-0945 © Year. The Authors. Published for Malaysia Institute of Planners. This is an open-access article under the CC BY-NC-ND license.
The authors hold the copyright without restrictions and also retain publishing rights without restrictions.